Hi folks,
we are currently experiencing an unplanned power outage in our datacenter.
It looks like the UPS failed in a way which prevented the automatic bypass to work.
We bypassed it now manually and will restart all machines during the day.
The buildfarm, buildbot and catalog generation are currently down.
The primary mirror and Mail are not affected.
Sorry for the inconvenience
— Dago
--
"You don't become great by trying to be great, you become great by wanting to do something,
and then doing it so hard that you become great in the process." - xkcd #896