Power Outage

Dagobert Michelsen dam at opencsw.org
Wed May 10 15:43:03 CEST 2017


Hi,

Am 10.05.2017 um 09:09 schrieb Dagobert Michelsen via maintainers <maintainers at lists.opencsw.org>:
> we are currently experiencing an unplanned power outage in our datacenter.
> It looks like the UPS failed in a way which prevented the automatic bypass to work.
> We bypassed it now manually and will restart all machines during the day.
> 
> The buildfarm, buildbot and catalog generation are currently down.
> The primary mirror and Mail are not affected.

Power has been restored and everything should work again.
If you encounter anything suspicious just let me know.


Best regards

  — Dago

--
"You don't become great by trying to be great, you become great by wanting to do something,
and then doing it so hard that you become great in the process." - xkcd #896

-------------- next part --------------
A non-text attachment was scrubbed...
Name: signature.asc
Type: application/pgp-signature
Size: 841 bytes
Desc: Message signed with OpenPGP
URL: <http://lists.opencsw.org/pipermail/buildfarm/attachments/20170510/7cbea6ea/attachment.asc>


More information about the buildfarm mailing list